It's a shame this will be covered up by the floor. It reminds me of a labryinth.
The open cells can be knocked out if needed for ductwork.
The rear area will be backfilled for the garage.
The basement floor is poured, with an interior drain in the center.
Saturday, July 26, 2008
Thursday, July 17, 2008
Wednesday, July 16, 2008
Crawlspace backfilled.................
Earth is backfilled & tamped at foundation wall. Notice the anchor bolts at the front pier. These will secure steel columns for the "living roof" portion of the house. This section will be all steel commercial construction.
Because the perimeter was designed to even increments of 16", there was relatively little wasted block. I'm placing the smaller flat pieces in the construction driveway, where they break into even smaller pieces among the existing rocks.
Tuesday, July 15, 2008
Cells are filled...................
Sunday, July 13, 2008
Recyclables...................
Foundation walls...............
This high tech Solar Glove Dryer is
a must for every construction site.
I'll apply for a patent when I have more time.
Future occupants arrive to inspect progress.
The perimeter foundation wall is complete awaiting concrete to be poured into the cells of the block. This view is from the front door towards the basement ( workshop ) below the master bedroom. The remaining crawlspace will be conditioned to control moisture. Air conditioning ducts will be in the crawlspace, which is much more energy efficient than the attic.
a must for every construction site.
I'll apply for a patent when I have more time.
Future occupants arrive to inspect progress.
The perimeter foundation wall is complete awaiting concrete to be poured into the cells of the block. This view is from the front door towards the basement ( workshop ) below the master bedroom. The remaining crawlspace will be conditioned to control moisture. Air conditioning ducts will be in the crawlspace, which is much more energy efficient than the attic.
Subscribe to:
Posts (Atom)